![](https://blogs.egusd.net/measurem/files/2019/03/Elitha-Donner-Elementary-ps-edited-6-5-2018-1fp57ef.jpg)
Elitha Donner Elementary
Project Address: 9461 Soaring Oaks Dr, Elk Grove, CA 95758
Project Dates: March – August 2019
Updates & Renovation
Shade Structure
Installation of an outdoor shade structure to include accessibility improvements and concrete pads.
Contractor: A.M. Stephens Construction Co., Inc. (Lodi, CA)
![](https://blogs.egusd.net/measurem/files/2017/07/09_25_2018_Elitha_Donner_Elementary_School_Job_Site_Progress_Report-2krrv5c.jpg)
Completed Works
Throughout the years this site has updated or reinstalled Roofing Construction Accessibility options
Roofing
Project Dates: March – November 2018
Overlay of the existing roofs with a new Energy Star rated, single-ply system on the administration, kindergarten, library, multi-purpose, and E wing buildings.
Contractor: Commerical Waterproofers, Inc. (Sacramento, CA)
Shade Structure
Project Dates: March – August 2019
Installation of an outdoor shade structure to include accessibility improvements and concrete pads.
Contractor: A.M. Stephens Construction Co., Inc. (Lodi, CA)
As of now there will be no more updates or none of note For this Site