Barbara C. Morse Elementary

Project Address: 7000 Cranleigh Ave, Sacramento, CA 95823

 

Updates & Renovation


Roofing

Project Dates: March – September 2019

New, mechanically fastened single-ply roofing installed on the library, administration building, K1 and K2 (kindergarten) classrooms, multi-purpose room, and classrooms in the A through E wing buildings.

Contractor: King’s Roofing (Sacramento, CA)

Shade Structure

Project Dates: October 2019 – February 2020

Installation of an outdoor shade structure to include accessibility improvements and concrete pads.

Contractor: A.M. Stephens Construction Co., Inc. (Lodi, CA)

Security System Upgrade

Project Dates: July 2019 – April 2020

Installation of new security cameras with associated materials and software. The school is one of six (6) pilot sites at which a new security camera system will be implemented and evaluated for its suitability of use at EGUSD sites district-wide. Installation will be completed by the end of 2019 with system testing during the first quarter of 2020.

Contractor: Trofholz Technologies, Inc. (Rocklin, CA)