Foulks Ranch Elementary
Project Address: 6211 Laguna Park Dr, Elk Grove, CA 95758
Updates & Renovation
HVAC
Project Dates: September 2019 – March 2020
Replacement of twenty-three (23) rooftop HVAC units and fifteen (15) Bard units with the addition of economizers to nine (9) existing rooftop HVAC units and all associated work.
Contractor: Kaler Dobler Construction, Inc. (Roseville, CA)
Project Address: 6211 Laguna Park Dr, Elk Grove, CA 95758
Updates & Renovation
HVAC
Project Dates: September 2019 – March 2020
Replacement of twenty-three (23) rooftop HVAC units and fifteen (15) Bard units with the addition of economizers to nine (9) existing rooftop HVAC units and all associated work.
Contractor: Kaler Dobler Construction, Inc. (Roseville, CA)
Alarm and Clock System Replacement
Project Dates: April – November 2019
Fire alarm and clock systems replaced with upgraded technology.
Contractor: Vanden Bos Electric, Inc. (Roseville, CA)
Roofing – Phase 2
Project Dates: March – August 2018
Overlay of existing roofs with a new Energy Star rated, single-ply system on the administration, kindergarten, library, multi-purpose building, A/E/F wings, and classrooms D1-D5, D7 and D8.
Contractor: Commerical Waterproofers, Inc. (Sacramento, CA)
Roofing/HVAC
- Foulks Ranch Elementary (HVAC)
Shade Structures
Installation of all-steel shade shelters to protect playground and outdoor seating areas from excessive heat and sun. Structures will be permanently mounted on a concrete pad