HVAC

Project Dates: September 2019 – March 2020

Replacement of twenty-three (23) rooftop HVAC units and fifteen (15) Bard units with the addition of economizers to nine (9) existing rooftop HVAC units and all associated work.

Contractor: Kaler Dobler Construction, Inc. (Roseville, CA)

Alarm and Clock System Replacement

Project Dates: April – November 2019

Fire alarm and clock systems replaced with upgraded technology.

Contractor: Vanden Bos Electric, Inc. (Roseville, CA)

Roofing – Phase 2

Project Dates: March – August 2018

Overlay of existing roofs with a new Energy Star rated, single-ply system on the administration, kindergarten, library, multi-purpose building, A/E/F wings, and classrooms D1-D5, D7 and D8.

Contractor: Commerical Waterproofers, Inc. (Sacramento, CA)

Roofing – Phase 1

Project Dates: July – August 2017

New roof installed on B & C Wing buildings to stop ongoing leaks and further damage to structures.

Contractor: California Single Ply, Inc. (Rocklin, CA)