Construction is under way, our shade structure should be complete and the temporary fence should be removed by 10/4 according to the construction schedule.

Shade Structure Construction Schedule:

  1. September 12 Construction Plus Dig Footings
  2. September 13 Construction Plus Set Rebar Cages
  3. September 16 Construction Plus Pour Footings
  4. September 23-25 Construction Plus Build Shade Structure
  5. September 26 – 30 Popuch Concrete Flatwork
  6. October 1st   Stephens Decomposed Granite
  7. October 2nd Stephens Landscape Restoration
  8. October 3rd Stephens Asphalt Patch Back
  9. October 4th  Stephens Remove Temp Fence